Darcos (Thomas & Pedro)
Ceiling joints — all roomsComplete
Self-levelling screedMon Apr 13 ✓
Metal louvre wall — quotes ×3Urgent
Yosima 2nd batch (25 buckets)Delivered
Julio (Tadelakt / Yosima)
Personal emergency late May — back on site 1 Jun, applying yellow primerResolved
Yosima colours: MH walls SCBR 3.3 / shoe closet GRGE 4.2 / MH ceilings BR 4 / GH SCBR 2.3Confirmed 1 Jun
Materials: Die Gelbe 10L ×7 + Claytec 13×25kg (yoga)Ordered
GH after Julio finishes there late June / early JulyPedro coordinating two teams
Nuno / Impact Method (Mortex / Waterproofing)
Scope: MH Mortex + HH kitchen/bathroom (Beal); self-levelling + waterproofingConfirmed
Finish: F2 floors/wet floors/kitchen; bath tub F2, walls above line F4; rest F4 + varnish/waxAgreed 22 May
Full quote (incl. possible Yosima contingency)Finalising this week
Mapelastic waterproofing + new shower drains coverageIn progress
Lucas (Capote)
FB report: wrong adhesive (A96), missing corner profiles, short/missing plugs, mesh to removeDefects confirmed
Raoul offered €13,800 refund settlement OR redo w/ FB trainingDeadline was 26 Jun
Lucas says returns early July w/ own people; Tomás (Darcos) can followPlan B live
Backup hunt: Obras Gonçalves (no answer); Fassa contacts pendingTomás f/up Thu 2 Jul
Helder (RAL / Lighting)
Keep current items, return trimless ringsConfirmed
Mini trimless countPedro to confirm
Apr 24 site visit (Helder + António)Done
Ajax Photo Detector pairedDone