#19 Nuno — awaiting quote confirmation
Waiting on Nuno
Revised quote replied. Oat Mid (BM2050) confirmed for all surfaces (17 May). Soft/rounded edges + GH bath ceiling trowel shaping (like Julio's MH living/bedroom) reminded to Nuno. Mortex curing = 7 days — orchestrate carefully.
PedroMain HouseFollow Up · May 20
#115 Bruma "Torneiras de passagem 3/4"
Overdue May 8
8 Elo (MH/HH) + 2 Imperial (GH); ref 125301. Caixa de passagem 3/4 installed but torneira not yet. Raoul re-orders via Astolfi if still missing.
PedroMain HouseCritical · May 8
#75 Finalise Interiors G-Sheet checklist
May 27
Plaster + sand ceilings, fireplace plaster.
PedroMain HouseCritical · May 27
#51 Western wall + metal louvre — design + suppliers
May 27
Break-ins in community — must be in before move-in. Spec 180cm stepped, 10cm × 2mm louvres, 5mm overlap, 3cm spacing, 30°, 5mm L-bracket. Gates max 1.8–2m, taller for car/pedestrian, recessed entrance gate. Raoul developing project; detailed drawings next.
PedroGardenCritical · May 27
#85 False ceilings GH + HH + GH kitchen
Overdue Apr 24
Linen closet ceiling = plaster only. Raoul to reach Mateus to confirm next site visit — GH bath false ceiling blocks Julio's tadelakt.
Pedro / RaoulCross-AreaFollow Up · Apr 24
#9 Waterproofing — mesh, drains, corners
Jun 3
Reinforced junction (tape) + small cove radius (5–10mm). Confirm timing with Nuno.
PedroMain HouseCritical · Jun 3
Jacuzzi heat pump — grill, colour, decibels, position
Overdue May 13
Pump position decided. Heat pump still open — Raoul asking João.
Pedro / RaoulGardenFollow Up · May 13
#113 Prep bathrooms for Nuno
May 28
Fill bathroom ceilings, install stone shelves, round edges 2mm radius.
PedroMain HouseCritical · May 28
#41 HH membrane — let plaster fully cure
May 30
Wait for plaster layers to be 100% cured and flush before applying membrane.
PedroHelpers HousePending · May 30
#16 Helder ceiling lights — mini trim count
May 31
Helder confirmed: keep current items, return trimless rings. Pedro to confirm mini trimless count before factory order.
PedroMain HouseFollow Up · May 31
#18 Capote — KEIM Stucasol agreed
Awaiting Lucas
KEIM Stucasol agreed for capote + garden walls. Awaiting Lucas reply on A24 / base-layer brand-consistency before proceeding.
PedroMain HouseCheck · May 20